GEV to Develop 2.8 GW Green Hydrogen Export Project Tiwi Islands, Australia: To Supply Japan, Korea and Singapore

By October 28, 2021 8   min read  (1462 words)

October 28, 2021 |

fuel cells works, GEV Scoping Study: C-H2 Supply Chain Will Be a Competitive Large-Scale Marine Hydrogen Transport Solution
  • Integrated With Compressed Hydrogen Shipping

GEV Acknowledges That Its Proposed Tiwi Islands Green Hydrogen Export Project Is Located on the Traditional Lands of the Munupi People. It Is a Privilege to Have the Support and Such a Close Working Relationship With the Tiwi Land Council and Munupi Landowners.

Highlights

  • GEV to develop a green hydrogen export project located on the  Tiwi  Islands,  Northern  Territory,  with a  phased capacity of up to  2.8  GW  (the  Tiwi  Hydrogen  Project),  producing up to  100,000  tonnes per annum green hydrogen for export into the  Asia-Pacific region.
  •  The  Tiwi  Hydrogen  Project will deliver a  fully integrated green hydrogen production and export supply chain,  commencing with a  fleet of GEV’s 430t  compressed hydrogen ships.
  • Selection of the  Tiwi  Islands location provides a  brownfield site that can reduce development time and cost and access to one of the closest  Australian ports  (owned by  AusGroup Limited’s NT Port and  Marine)  to the future demand markets in the  Asia-Pacific region.
  • The integration of GEV’s innovative compressed hydrogen shipping solution enables a  phased development and construction timeframe,  thereby benefiting from the continued decline of the capital and operating costs for solar generation,  electrolysers and shipping.
  • The Tiwi  Hydrogen  Project supports critical stakeholders,  including the  Tiwi  Land  Council,  the Munupi  Landowners,  NT  Port and  Marine and the  Northern  Territory  Government.
  • Development milestones of the  Tiwi  Hydrogen  Project will run in parallel to GEV’s ship engineering and class approval program,  with a  financial investment decision targeted for  2023  for the initial phase being  0.5  GW,  allowing the first hydrogen export to commence in  2026,  subject to all commercial and regulatory approvals and customer offtake.

Global  Energy  Ventures  Ltd  (ASX:  GEV,  the  Company)  is  pleased  to  announce  the  development  of  a  2.8  GW  / 100,000  tpa  of  green  hydrogen  export  project  on  the  Tiwi  Islands,  Northern  Territory,  Australia  (the  Tiwi Hydrogen  Project).  GEV  is  proposing  a  staged  approach  to  construction,  with  an  initial  development  phase  of ~0.5  GW  of  installed  solar  generation,  expanding  to  2.8  GW  as  the  regional  hydrogen  market  grows,  as  well  as benefitting  from  the  ongoing  cost  and  efficiency  improvements  in  photovoltaics,  electrolysers  and  shipping.

GEV’s  Managing Director  and  CEO, Martin  Carolan  commented:  “The  strategic  rationale  for  GEV  to  develop  a landmark upstream renewable energy and green hydrogen production project is to demonstrate the simplicity  and efficiency  of  using  compression  for  a  pipe-to-pipe  green  hydrogen  supply  chain  and  to  provide  greater  certainty in  the commercialisation of  our shipping solution.  This project  can  transition  GEV  from a midstream service provider to  an  innovative  hydrogen  company.

“Our  compressed  shipping  solution  is  highly  modular  and  can  therefore  scale  to  match  the  advancement  of electrolyser  technologies  and  market  demand  for  pure  green  hydrogen  gas,  and  deliver  a  competitive  cost  of hydrogen as  the project  scales.  The  support  of  the  Northern  Territory  Government  also  demonstrates  the  Territory’s strategy  and  vision  to  be  a  world-scale  producer  and  exporter  of  renewable  hydrogen.”

Northern  Territory  Government  Minister  for  Renewables  and  Energy,  Hon  Eva  Lawler  commented: “I  welcome  GEV’s  announcement  that  it  has  selected  the  Tiwi  Islands  for  its  renewable  hydrogen  project  and  that it  is  working  closely  with  the  Tiwi  Land  Council  and  the  Traditional  Owners  of  the  land.  With  our  world-class  solar resources  and  our  proximity  to  key  export  markets,  the  Northern  Territory  is  an  ideal  place  to  generate  renewable hydrogen  to  meet  the  future  demand  within  our  region.

“We  look  forward  to  supporting  GEV  through  our  investment  facilitation  team  to  progress  the  project  through  to operation.”

Fuel Cells Works,

Figure 1: Tiwi Hydrogen Project Overview

Major Benefits of the Tiwi Hydrogen Project GEV’s

Executive Director and Chief Development Officer, Garry Triglavcanin commented: “Today’s announcement of the Tiwi Hydrogen Project is the result of over six months of research, analysis and consultation to gain the support of key stakeholders, including the Tiwi Land Council, the Munupi Landowners, Northern Territory Government, Tiwi Plantation Corporation, NT Port and Marine and a number of technology vendors. I would like to personally thank the Tiwi Land Council and the Munupi Landowners for welcoming GEV to the Tiwi Islands and their ongoing trust and support. The project will deliver social and economic benefits to the Tiwi community in the form of employment, skills training and education on a long-term sustainable basis.

GEV has worked closely with key Tiwi stakeholders to ensure the project will have a low environmental impact on the Tiwi Islands. This has been achieved by selecting previously cleared and developed plantation land for the solar farm, existing right of way for the transmission line, as well as locating the hydrogen production facilities at an existing industrial precinct, adjacent to existing port infrastructure for export. GEV has completed a pre-feasibility level analysis that has identified this location as being highly suited to our compressed hydrogen shipping solution due to its close proximity to Asia-Pacific markets.”

  • LOCATION:  the  Tiwi  Islands  are  located  along  the  northern  most  part  of  Australia,  providing  GEV  with  a strategic  location  for  regional  shipping  to  the  emerging  hydrogen  markets  across  the  Asia-Pacific,  including Singapore,  Indonesia,  South  Korea  and  Japan  (see  Figure  2).
  • HIGH SOLAR CAPACITY / INTENSITY:  the  proposed  1,800  hectare  solar  site  has  been  assessed  to  have  the potential  for  2.8  GW  of  solar  generation, in  a  region  of high  solar  intensity.
  • LOW ENVIRONMENTAL  IMPACT:  the  proposed  solar  site  is  existing  plantation  land,  previously  cleared  of native  vegetation  and  currently  used  for  commercial  plantation  (see  Figure  1).  The  proposed  solar  site represents  only  6%  of  the  existing  plantation  area  and  only  0.3%  of  Melville  Island  land  area.  In  regard  to water supply for the initial  phase of  the  project,  the  electrolysers  are  anticipated  to  consume  up  to  550  m3/day of  demineralised  water  for  hydrogen  production.    Small-scale  desalination  facilities  will  be  installed  (seacontainer  sized),  with  GEV  also  seeking  to  maximise  the  potential  of  local  water  catchment.
  • PORT INFRASTRUCTURE: there is availability and access to existing port infrastructure and industrial precinct at  Port  Melville  (owned  by  AusGroup  Limited’s  NT  Port  and  Marine),  capable  of  berthing  GEV’s  fleet  of compressed hydrogen 430t pilot  scale  ships.  GEV  to  introduce  its  full  scale  2,000t  ships  as  required  to  match future  supply  and  demand  (see  Figure  1).
  • COMPRESSION:  utilising  compression  as  the  method  to  load,  store  and  transport  hydrogen  avoids  the complex  and  capital  intensive  process  to  ‘pack  and  unpack’  pure  hydrogen  gas  required  by  other  carriers such  as  LH2,  NH3  or  LOHC. This  is  an  important consideration  for  the  customer  end  of  the  supply  chain. >
  • NT GOVERNMENT SUPPORT: GEV has the support of the Northern Territory Government, and GEV will seek federal  infrastructure  funding  and  support  given  the  new,  sustainable  industry  and  economic  opportunities for  the  indigenous  communities  on  the  Tiwi Islands  and  Territorian  people  in  general.
Captura de pantalla 1462

Figure 2: Tiwi Hydrogen Project proximity to Asia Pacific export markets

Major Benefits Of The Compressed Hydrogen Supply Chain

  • The scalable nature of compression allows GEV to propose a staged approach to construction, with an initial development phase of ~0.5 GW of installed solar generation, expanding to 2.8 GW as the regional hydrogen market grows. This allows GEV and its customers to benefit from the ongoing cost and efficiency improvements in photovoltaics, electrolysers and shipping.
  • The Tiwi Hydrogen Project leverages the unique benefits of GEV’s compressed hydrogen shipping solution, meaning no requirement for costly onshore hydrogen storage and minimal battery storage (as the production and loading of hydrogen will “load follow” the daily and seasonal solar generation profile).
Captura de pantalla 1463

Figure 3: Tiwi Hydrogen Project Supply Chain

 

Next Steps

  • GEV has and will continue working with the Tiwi Land Council and Munupi Landowners, given the responsibility to ensure that the Tiwi Hydrogen Project delivers community benefits to the Tiwi people, in the form of leasehold payments, employment, and supporting power and water infrastructure.
  • GEV to fast track the installation of solar monitoring stations at several locations, allowing GEV to establish bankable solar generation data for the proposed project location.
  • GEV to continue working with the Tiwi Plantation Corporation, Tiwi Land Council and Munupi Landowners to progress securing a Section 19 Lease/Licence over the proposed solar site. As the solar site has previously been cleared of native vegetation and zoned for plantation use.
  • GEV to continue working with NT Port and Marine (a subsidiary of AusGroup Limited) to integrate Port Melville’s operations and facilities into the Tiwi Hydrogen Project.
  • GEV to commence planning for a full feasibility. Including further information on the project development schedule, technical partners, project scale, solar monitoring activities and appointment of consultants. The project schedule will run in parallel with GEV’s ABS full class approval program for the 430t pilot scale ship.
  • Financial close for the initial phase of the Tiwi Hydrogen Project is targeted for 2023, with first hydrogen export to commence in 2026, subject to all commercial and regulatory approvals and customer offtake.