Frontier Energy: Pre-FEED Confirms Costs and Viability for Stage One Green Hydrogen Facility at Bristol Springs Project

By December 19, 2022 6   min read  (932 words)

December 19, 2022 |

Fuel Cells Works, Pre-FEED Confirms Costs and Viability for Stage One Green Hydrogen Facility at Bristol Springs Project

Frontier Energy Limited (ASX: FHE; OTCQB: FRHYF) (Frontier or the Company) is pleased to announce the completion of the Pre-Front End Engineering Design (“Pre-FEED” or the “Study”) relating to the proposed hydrogen facility to be built at the Company’s Bristol Springs Renewable Energy Project (the “BSS Project”) in Western Australia.

The Pre-FEED study was completed to provide a higher level of definition from the pre- feasibility study. The hydrogen production plant project cost estimate was completed to a Class 4 level of certainty and confirmed the operating and capital costs were in-line with the Pre-Feasibility Study (PFS) (ASX Announcement 4 August 2022). The Pre-FEED also included potential for compression and storage, which was completed to Class 5 level of certainty.

The Company is currently assessing all information regarding the Stage One development with the aim of releasing a Definitive Feasibility Study (DFS) during Q12023.

HIGHLIGHTS

  • The Company has completed the Pre-FEED for the Stage One (36.6MW) hydrogen facility at the Company’s BSS Project confirming the cost and viability of the facility
  • The Pre-FEED was completed by independent global engineering and construction firm, GHD. GHD was selected due to its vast experience in the hydrogen industry
  • Capital cost estimate for the construction of a 36.6MW facility (and associated infrastructure) was estimated at $71.7 million ($69.8 million in PFS)
  • Direct operating costs associated with the Hydrogen Facility were estimated at $2.89 million pa
  • These direct operating costs exclude water consumption. This cost is approximately $0.8m million per annum pursuant to the Water Corporation water supply agreement (in-line with the PFS estimate)
  • The Pre-FEED did not identify any technical barriers for the development of the Project
  • The Company is now advancing the Stage One development towards a Definitive Feasibility Study that is on track to be completed during 1Q2023

Managing Director, Sam Lee Mohan commented: “We are delighted with the outcome of the Pre-FEED as both capital and operating costs are in-line with the PFS estimates, despite the higher degree of certainty with estimates in the Pre-FEED (compared to the PFS) at a time when inflation globally is still at record high.

More importantly, however, was that GHD found there were no technical issues or other technical   barriers   with   the   development  of   the   hydrogen   facility   at   the   Project.   The Company is currently compiling all updated information since the release of the PFS as we advance Stage One towards a DFS to be released during Q12023.

Bristol Springs Renewable Energy Project advances towards a DFS following strong Pre-FEED for hydrogen facility

Following the completion of the positive Pre-Feasibility Study (PFS) for the Stage One Hydrogen   Project,   which   outlined   a   114MW   solar   farm   to   power   a   36.6MW   alkaline electrolyser, the Company engaged global engineering firm, GHD to complete Pre- Front end Engineering Design (Pre-FEED) assessing a hydrogen production facility including a 36 MW electrolyser.

GHD Pre-FEED study was completed with the following scope and assessment:

  • 36 MW Alkaline Electrolyser;
  • Future potential plug-and-play infrastructure for hydrogen compression system (up to 400 bar);
  • Future potential plug-and-play infrastructure for hydrogen storage systems to store 5 days (79 tonnes) of production;
  • Hydrogen export facilities via the following options:
  • Blending into the Dampier Bunbury Natural Gas Pipeline;
  • Road export via hydrogen truck trailer;
  • Provision for use in a future onsite 10MW Fuel Cell system;
  • Utilities including water, wastewater, and drainage;
  • Power;
  • On Site Infrastructure including major equipment buildings, warehouses and offices;
  • Plug-and-play for expansion up to 150MW. The outcome of this work resulted in the following:
  • Operating costs estimates for the hydrogen facility total $3.69 million per annum

compared to $3.5 million pa in the PFS or a 5% increase. These costs relate to direct operating costs only and excludes the cost to acquire additional electrons from the power grid;

  • Capital costs for the construction of a 36.6MW facility and associated infrastructure were estimated at $71.7 million, compared to $69.8 million in the PFS or a 3% increase; and
  • Pre-FEED did not find any technical barriers to development of the Project.

Capital Estimate

The PRE-FEED estimate for the total direct capital costs of a 36.6MW Hydrogen facility was

$71.7 million. A breakdown of the cost estimate is detailed below. The Pre-FEED also includes pre-production costs of $3 million.

Fuel Cells Works, Pre-FEED Confirms Costs and Viability for Stage One Green Hydrogen Facility at Bristol Springs Project

The capital estimate provided is based on GHD’s custom template. Quantities were taken off  concept  designs  in  conjunction  with  preliminary  Basis  of  Design,  detailed  in  the  Study. Cost estimates were derived from various techniques including vendor quotes, budget quotes and historical projects in regional WA estimated or executed in the last 0-3 years.

Operating Costs

The PRE-FEED Class 5 estimate for total direct operating cost on an annualised basis for a 36.6MW Hydrogen facility was $2.89 million per annum. A breakdown of the cost estimate is detailed below.

Fuel Cells Works, Pre-FEED Confirms Costs and Viability for Stage One Green Hydrogen Facility at Bristol Springs Project

This cost estimate above is exclusive of water costs which were included in the total direct operating costs of $3.5 million in the PFS estimate. Through negotiations with the Water Corporation, the estimated water cost is approximately $0.8 million per annum based on expected consumption.

Authorised for release by Frontier Energy’s Board of Directors.

Read the most up to date Fuel Cell and Hydrogen Industry news at FuelCellsWorks

About Frontier Energy

Frontier Energy Ltd (ASX: FHE; OTCQB: FRHYF) is developing the Bristol Springs Green Hydrogen Project (the Project) located 120km from Perth in Western Australia.

The Company recently completed a Pre-Feasibility Study1 that outlined the Project’s   potential   to   be   both   an earlier mover and one of the lowest cost green hydrogen assets in Australia.

The  Project  benefits  from  its  unique location surrounded by major infrastructure. This reduces operating and capital costs compared to more remote hydrogen projects, whilst also being surrounded by likely early adopters into the hydrogen industry in the transition from fossil fuels.