PERTH, AUSTRALIA Hazer Group (ASX: HZR) is pleased to provide the following update on the progress, cost and schedule of the Hazer Commercial Demonstration Project (CDP) being constructed at Water Corporation’s Woodman Point Water Recovery Facility. The CDP will be the firstofitskind, fully integrated, operational production facility based on the Hazer Process and represents the key next step in fully commercialising the Hazer technology.
Progress continues with engineering, procurement, fabrication and construction activities achieving milestones in civil construction and commencement of mechanical construction.

Hazer Group Update
Fabrication of process modules and equipment items has progressed at vendor sites, with many packages now either completed and received into storage or completed and being held at vendor sites until required onsite. Key equipment packages that have been completed include; Biogas Pretreatment Unit, Compression Equipment (Process and Recycle Compressors), Cyclone and Filter Package, Graphite Screw Conveyors, Process Conveyors, Gas Chromatograph and Analysers, flare packages and catalyst lift crane. Transformer equipment required for the connection to grid has been secured and the installation schedule agreed with Western Power.


Civil construction activities have progressed well, with deep foundations, trenching and main underground cabling activities completed. Civil construction works are expected to be completed in the first week of September with the completion of final concreting works. Mechanical construction has begun with commencement of work on pipe racks and main structure and installation of mechanical equipment related to the Biogas PreTreatment Unit (CO2 removal unit).


While most project items have remained on schedule, we have seen delays with the fabrication and supply of high temperature materials required for the main reactor vessel, hightemperature heat exchangers and hightemperature piping. These delays have occurred due to disruption related to Covid19 related restrictions in  China impacting mill operations, and the impacts of Typhoon Infa on scheduled shipping deliveries between China and Australia. The fabrication of the main reactor shell has been delayed due to changes in the production schedule of the selected mill. While we are yet to finalise the expected delivery date for the reactor vessel to the Australian fabricator for detailed completion, we expect that the delay will result in the overall project schedule slipping. We now estimate that commissioning of the project will be achieved in Q1 2022, rather than our previous target date of December 2021.


We maintain our current guidance of $21 $22 million for the cost of the CDP. We will work closely with our engineering partner, Primero, to minimise any additional costs incurred through the anticipated delay or increased shipping and freight costs to ensure that we maintain efficient productivity through the construction  and installation activities.


Geoff Ward, Chief Executive Officer of Hazer Group said “We remain pleased with the progress of the CDP, in particular achieving the completion of main civil works and commencement of mechanical construction. We are also pleased that key equipment items and modules are now being completed and delivered to site. The Hazer reactor and furnace is a complex, firstofkind equipment package which is being made more challenging by the current operating environment with significant disruptions to supplier operations and freight schedules due to the global Covid19 pandemic, which has impacted the delivery time of hightemperature materials for the reactor and heat exchangers. We will continue to monitor these issues and do all we can to mitigate the  impacts on the project.